Vestas Wind Turbine Arc Flash Accident

Vestas has released the findings of the investigation into what caused one of itsV112-3.0 MW wind turbines to catch fire on March 30.

According to the company, the fire started in the harmonic filter cabinet as aresult of a loose connection in the electrical system that created an arc flash.

To resolve the problem, Vestas says it will use a different type of washer on the electrical connections in the harmonic filter cabinet.

The solution is in the process of being implemented in the affected turbines, and customers are being informed. At the site, the burned nacelle has been replaced and is scheduled to be commissioned next week.

Most of the paused V112 turbines have been restarted or are in the process ofbeing restarted. Vestas says that as it returns the paused turbines to normal operations, it has also rescheduled and moved forward on already-planned upgrades. These upgrades are not related to the root cause, but rather preventative maintenance.

Vestas expects that all of the paused turbines will be returned to normal operationby the end of the month.

The company is also awaiting the reports from two external experts who workedside by side with Vestas investigators. These reports are expected within a fewweeks.

Source via North American Wind Power

Advertisements
  1. No comments yet.
  1. No trackbacks yet.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: